Processing of the air duct
Metal duct processing
Air duct and accessories should be made with mature technology and process, and adopt mechanical processing methods with high efficiency, low consumption and low labor intensity.
The production size, interface form and flange connection mode of the air duct and accessories have been clear, the processing scheme has been approved, and the technical standards and quality control measures adopted are complete.
Production of rectangular air duct
For the expansion and discharge of the rectangular duct, one side is the circumference, which is the sum of the sides of the rectangular section, and the other side is the length of the duct. Before manual line cutting or mechanized production, the material used shall be checked. The ines shall be drawn according to the shape and specification of the construction drawing and the sample drawing of the duct.
The expansion drawing of the duct should be strictly angular to avoid the distortion and warping of the duct. The cutting of the plate is the process of cutting the plate according to the line shape. The folded edge of the duct is folded into a right Angle with a manual plate edge machine, and then the bite mouth is compacted into a rectangular duct.
Reinforcement of the air duct
- Objective: The duct with large diameter or side length should avoid the duct section deformation and reduce the noise generated by running vibration.
- The reinforcement of the circular air duct: its own high strength, generally not reinforced.
- If the diameter of the circular duct is greater than or equal to 800mm, and the length of the section is greater than 1250mm or the total surface area of the section is greater than 4m², add a flat steel reinforcement ring every 1500mm and fix it to the duct with rivets.
- If the diameter of the circular duct is greater than 500mm, both ends of the longitudinal bite shall be fixed with rivets or spot welding.
- Reinforcement of rectangular air duct: low strength and easy to deform.
When the large side length of the rectangular duct is greater than or equal to 630mm, the large side length of the insulation duct is more than 800mm, the pipe length is more than 1250mm, or the single flat area of the low pressure duct is more than 1.2m², and the medium and high pressure duct is more than 1.0m², reinforcement measures shall be taken.
Making of the circular air duct
The processing of the circular air duct is usually done either by hand or mechanically. Before manual processing, the cut plate should be pressed on the round tube, and then trimmed with a wooden ruler, so that the bite can be buckled to each other, and then the bite tightly, and finally with a square ruler, until the arc is even. Mechanical processing is to roll the rolling machine, the plate through the rolling machine, and then by the bite machine compaction, become a circular duct.
Number of rectangular duct corner bites
In the processing of the rectangular duct, when the circumference of the duct is less than the plate width, an angular bite can be set. When the plate width is less than the circumference of the duct, more than half of the circumference, two corners can be set. When the circumference is very large, four corners can be set in the four corners of the air duct.
Composite air duct fabrication
Construction conditions
The production size, interface form and flange connection mode of the air duct and accessories have been clear, the processing scheme has been approved, and the technical standards and quality control measures adopted are complete.
The production environment of the field air duct shall meet the operation requirements, and mechanical ventilation shall be adopted.
The material meets the technical standards of relevant products, the performance of plate and adhesive meets the production requirements, match the function of the air duct system, and the material passes the field inspection.
Processing machines and tools are all ready to meet the production requirements.
Air duct production
Lofting and feeding shall be carried out on a flat and clean working table, and shall not destroy the covering layer.
The four sides of the rectangular aluminum foil composite insulation duct can be made of 90 gaps on a plate, or they can be made of 45 degrees of two plates.
The width of the plate is 1.2m, and save materials as much as possible. The duct is 4 meters long as far as possible to reduce the duct interface.
After the plate feeding is finished, the splicing. The corner of the splicing should be straight, check the joint into 90 degrees, and then adhesive when it is correct.
Allowable deviation of air duct (mm)
| Pipe long side size b or diameter D | allowable deviation | ||||
| Side length or diameter deviation | Surplanness of rectangular duct | The difference between the diagonal lines of the rectangular duct port | Flange or port end plainness | Circular flanges are arbitrarily orthogonal to two diameters | |
| b(D)≤320 | ±2 | 3 | 3 | 2 | 3 |
| 320<b(D)≤2000 | ±3 | 5 | 4 | 4 | 5 |
After the combination of composite air duct, the same plate should be attached to the aluminum foil tape, and the sealing width should not be less than 20mm on each side.
When the nozzle of the composite duct is less than or equal to 630mm, the same material of these ports can be directly bonded (the interface is made of 45 degrees corresponding to the incision bonding). When the long side is less than 1250mm, UPVC connection plug can be used; when the long side is greater than 1250mm, aluminum alloy flange plug connection must be used.
The composite duct should be reinforced with galvanized screw with a diameter of not less than 8mm for internal support, and the pipe wall of the inner support shall be sealed.
The processing of the duct flange is connected with the air duct
Processing sequence of the air duct flange
Gauge material combination forming welding pair drilling.
Air duct flange cushion material
- Rubber plate-elasticity, good tightness, widely used.
- Asbestos rubber plate-good elasticity, high temperature resistance, suitable for smoke exhaust system.
- Soft PVC dilute board-corrosion resistance, poor thermal stability.
- Closed-hole sponge rubber plate- -high temperature resistance, acid and alkali resistance, good flame resistance.
- During use, the appropriate flange cushion should be selected according to the type of medium delivered by the air duct.
Connecting of the rectangular duct and corner steel flange
Method orchid is made of four-angle steel welding. When underlining, attention should be paid to the internal diameter of the flange after welding should not be less than the external passage of the air duct, with the steel cutting machine.
After straightening the feeding, put it on the punch bed to impact the rivet hole and the bolt hole, and the hole distance shall not be greater than 150mm. If 8501 flame retardant sealing strip is used as bedding, the bolt hole distance can be appropriately increased, but shall not exceed 300mm. Bolt holes shall be provided at the four corners of the flange.
After punching, the corner steel is placed on the welding platform for welding, and the mold is tightened according to each specification.
Material specification for the rectangular air duct flange
| Large length of rectangular duct (mm) | Material specification for Angle steel (mm) |
| ≤630 | L25×3 |
| 800~1250 | L30×4 |
| 1600~2500 | L40×4 |
| 3000~4000 | L50×5 |
Material specification of circular duct flange
| Circular air duct diameter | Material specification for flanges | |
| (mm) | flat-rolled steel (mm) | angle (mm) |
| ≤140 | -20×4 | |
| 150~280 | -25×4 | |
| 300~500 | 25×3 | |
| 530~1250 | 30×4 | |
| 1320~2000 | 40×4 | |
When processing the flange, the weld joints of the flange shall be well fused, full and without slag and holes; bolt holes shall be provided at the four corners of the rectangular flange in the center on the center line of the same size for the same batch processing, etc.
The connection of the rectangular air duct to the angle steel flange shall meet the following requirements:
The duct plate thickness is less than or equal to 1.2mm and the long side size of the duct is less than or equal to 2000mm shall be riveted when connection with the angle steel flange.
The flap of the duct should be close to the flange, and the width shall be uniform and not less than 6mm. The riveting shall be firm, 100-120mm apart, and the number shall not be less than 4.
Air duct plate with thickness greater than 1.2mm can be welded with corner steel flange. The air duct and flange should be close together, the end surface of the air duct shall not protruding from the flange interface plane, the length of continuous welding should be 30-50mm, and the spacing should not be greater than 50mm.
Common board flange air duct
Common plate type flange duct is also known as the impossible blue duct, its production form is better than the traditional rectangular duct processing speed is faster, more convenient, smaller air leakage rate.
Its advantages are saving materials, reducing project investment; small air leakage, reducing energy consumption and saving operating cost, very popular in construction enterprises.
Total plate flange is mainly composed of Angle code, flange, and flange connected with the air duct, this form of duct, although low cost (reduce the amount of Angle steel, reduce the production of Angle steel flange usage), but the practical application than Angle steel flange, air leakage is larger, and must be processed by machine tool, handmade almost, cannot realize its production, usually only applied to fresh air system, air conditioning system, etc., smoke exhaust system or often use Angle steel flange connection duct. But the civil air defense engineering is absolutely not allowed to use the common board flange connection.
Using Angle steel flange connection, consumes a lot of Angle steel, welding rod, bolts, paint and other materials, as well as a lot of labor; production accuracy, low work efficiency, production cost is high, and the production and installation quality of air duct is not easy to guarantee.
Connect the plug strip of the air duct
The side length of the connected with C-shaped flat and S-shaped flat strips shall not be greater than 630mm. When the S-shaped flat insert is used alone, there should be fixed measures at the connection. The C-shaped right-angle insert can be used to connect the branch pipe with the main pipe.
The side length of C-shaped and S-shaped vertical strips shall not be greater than 1250mm. The S-shaped vertical strip and the duct wall should be riveted with a spacing less than 150mm.
The connection between the plug strip and the air duct socket shall be smooth and tight. The horizontal strip length shall coincide with the duct width.
Aluminum plate rectangular duct should not be connected with C-shaped and S-shaped flat strip.
Suspension-type air duct is widely used:
Air duct double pipe and multi-pipe support and hanger are often suspended, and the air duct layout is generally horizontal and vertical direction. Double pipe and multi-pipe support hanger is also commonly used hanging Angle steel gantry bracket and hanging groove steel bracket.
U-shaped pipe clips or hanging ring may be fixed between pipes and support and hanger. When the round air pipe, water pipe and refrigerant pipe are supported by cross arm, the U-shaped pipe card is made with flat steel and round steel. U-shaped pipe card and cross arm are fixed by bolts; the insulation water pipe is set between the bracket and U-shaped pipe clips.
Cantilever and inclined support support and hanger:
Cantilever type and inclined support support and hanger should be installed on concrete walls, concrete columns and steel columns. The cantilever support and inclined support are made of Angle steel or channel steel, and the support, hanger and structure are fixed by embedded parts by welding or bolt.
Ground support bracket:
The ground support bracket is used for the landing installation of equipment and pipelines. The support is made of Angle steel and channel steel, and is firmly fixed with the ground or support bolts.
Anti-swinging bracket:
The anti-sway support does not shake due to the displacement of pipes or equipment. The hanger is made of Angle steel or channel steel, and is welded firmly with the root of the hanger and the cross arm.
Production of supporting hanger
The cantilever of the support and the hanger are made of angle steel or channel steel; the material of inclined support is angle steel; the boom is round steel; the flat steel is used to make the hoop.
New material: prefabricated support and hanger C-type steel
Features: not only the section shape is symmetrical, the bending modulus is improved, the upper opening has a serrated anti-skid groove, good safety performance, processing can be mass production, construction effect and construction safety, save labor cost.
Before the production of the support and hanger, the section steel should be corrected first, and the correction method is divided into two kinds of cold correction and thermal correction. Small steel generally adopts cold correction. The larger steel type shall be heated to about 900℃ for thermal correction. The order of correction should be corrected first, and then corrected for bending.
The weld seam of the bracket must be full to ensure sufficient bearing capacity.
The rod steel shall be properly appropriately according to the elevation of air duct installation. The sleeve should not be too long, and the end of the buckle should not exceed the lowest point of the tray.
After the production of air duct support and hanger, rust removal should be carried out and brush the anti-rust paint.
For the support of stainless steel and aluminum plate duct, the hoop should be anti-corrosion insulation according to the design requirements to prevent electrochemical corrosion.
Fixation of the hanger and building structure
According to the form of the hanger, the embedded parts method and the expansion bolt method are commonly used.
Pre-embedded parts method:
Generally, the reserved personnel will be embedded according to the drawing coordinates of the position and support, hanger spacing, firmly fixed on the civil structure reinforcement.
Burcrane under the floor: after determining the position of the crane, drill through the floor, and then pick a 300mm long and 20mm deep groove on the ground. Place the sling into the tank and fill the tank with cement mortar.
Expansion bolt method: characterized by flexible construction, accurate and fast.
Support, hanger and structure fixing can be fixed by expansion bolts, embedded parts welding and floor plate bolts. When there are no embedded parts in the structural cast-in-place plate, the hanger and the structural fixing point (the root of the hanger) are made of channel steel or Angle steel, which are fixed by the expansion bolts and the structure. The boom shall be bolted or welded to the channel steel or angle steel.
Installation of the hanger: the boom of the hanger should be straight with complete thread.
Find the laying position of the boom according to the center line of the duct, and the single boom is on the center line of the duct. The double boom can be installed symmetrically according to the spacing of the screw holes or the center line of the duct.
When the air duct is long, the need to install a row of brackets, the two ends of the first installation, and then to the two ends of the bracket as the benchmark, with the cable method to find out the elevation of the middle bracket for installation.
The boom can be connected or welded by thread. The connecting thread shall be 3 times longer than the diameter of the boom, and the welding shall be lap. The lap length shall be 8 times longer than the diameter of the boom, and both sides shall be welded.
Problems to be noted for the installation of supports and hangers
When the air duct is installed and the pipeline is long, a hanger should be added in the appropriate position to prevent swinging.
The elevation of the support and hanger must be correct. For example, the diameter of the circular air pipe changes from large to small. In order to ensure the level of the center line of the air pipe, the upper surface elevation of the support steel should be improved accordingly. For the duct with slope requirements, the elevation of the bracket shall also be installed according to the slope requirements of the air duct.
The embedded parts or expansion bolts of supports and hanger shall not be painted, and oil shall be removed.
The hanger shall not be installed in the air outlets, valves, inspection holes, etc., to avoid hindering the operation. The hanger shall not be hung directly from the flange.
The support and lifting device of the insulation duct should be placed outside the insulation layer, but the insulation layer shall not be damaged.
The insulation air duct can not directly contact with the support and lifting bracket, and should be padded with strong heat insulation material, its thickness is the same as the insulation layer, to prevent the generation of “cold bridge”.
Note for the production and installation of air duct support and hanger
Composite air duct installation:
The inner and outer surface of phenolic aluminum foil composite duct is coated aluminum foil, and the middle layer is phenolic foam material, which has good thermal insulation performance, light structure weight, excellent noise performance, long service life, health and environmental protection.
The installation period of phenolic composite duct is short, only about 1 / 5 of the traditional duct, which can make the project put into use as soon as possible and get benefits as soon as possible.
The production process of phenolic aluminum foil composite air duct is:
Quality inspection of connecting connector of bonding forming air duct and air duct.
(1) Plate lofting and feeding
Plate lofting feeding shall be carried out on a flat and clean working table, and shall not destroy the covering layer.
One-piece, U-shaped, L-shaped and four-piece methods should be used for plate lofting of rectangular duct.
The plate shall be straight.
(2) Air duct bonding and forming
When the long side size of the duct is less than or equal to 1600mm, the duct plate splicing can be directly bonded at 45 degrees Angle. The end surface of the duct after bonding forming shall be flat, and the planness and diagonal deviation shall meet the requirements of the specification. The duct is placed vertically to the set before moving.
(3) The plug connector is connected with the air duct
The connection of the phenolic aluminum foil composite duct is usually made with connectors. The length of the plug connector shall not affect its normal installation, and shall ensure its close contact when installed in two vertical directions of the air duct. The plug connector and the duct stick firmly.
The air duct should be made with galvanized screw with a diameter of not less than 8mm for internal support reinforcement, and the pipe wall of the internal support should be sealed. The number of transverse reinforcement points and the longitudinal reinforcement spacing of the internal support shall meet the requirements of the specification. For example, when the inner side length of the air duct is 800mm, and the designed working pressure of the system is 1000Pa, the number of transverse reinforcement points is 1, and the longitudinal reinforcement spacing is less than or equal to 600mm.
Composite duct installation follows the following process:
Measure the air duct and check the quality inspection of support and hanger installation combination connection air duct.
(1) Measure and set out the line
Before the installation of the air duct, the installation part should be measured to determine the position of the pipe center line.
Before installation, check the air duct for damage, cracking, deformation and other appearance quality defects, etc. The specification of the air duct shall correspond to the installation part, and the interface surface of the connector shall be free from damage.
(2) Air duct inspection
Before the installation, the duct shall be checked for damage, cracking, deformation, scratches and other appearance quality defects. The specification of the duct shall correspond to the installation site, and the surface of the composite duct socket and connector interface shall be free from damage.
(3) Support and hanger installation
The number of supports and hangers shall be arranged according to the spacing and setting requirements according to the site conditions. Determine the length of the boom according to the air duct installation height.
After the installation of the boom, the air pipe should be installed on the cross arm of the hanger and adjust the height of the duct through the screws on the boom.
(4) Combined connection
The air duct installation adopts the method of lifting in place, and the general installation sequence is the first main pipe and then the branch pipe. When using manual operation, the pipe section should be raised in a single section to prevent the air duct damage caused by uneven force. When conditions permit, two sections of FRP duct with side length (or diameter) greater than 1250mm may be lifted, and those with side length (or diameter) less than 1250mm shall not exceed three sections. When the side length of the air duct is greater than 2000mm, the steel pad of 100*1.2mm is set on the cross arm to increase the contact area and reduce the local load.
Tie the air duct firmly with hemp rope before lifting. If the plastic duct needs to be lifted as a whole, the rope shall not be directly tied to the duct, the bottom of the duct should be held by the long board, and there should be soft material around the cushion before lifting.
(5) Air duct adjustment
After the air duct is placed in the support and hanger, connect all the trays and the boom to confirm that the air duct is stable and the rope buckle can be unfastened.
The duct shall be adjusted after installation, and shall be straight and hanger shall be straight.
Note during installation: the duct interface shall not be installed in the wall or floor. When the duct is installed along the wall or floor, the distance from the wall and floor should be greater than 150mm.
Anticorrosion and insulation of air duct:
Insulation material requirements
(1) The insulation of the air duct and pipe shall be made of non-combustible or non-combustible materials, and the material, density, specifications and thickness shall meet the design requirements. If the flame retardant material is used, the flammability should be checked and can be used after qualified.
Inspection quantity: 1 piece is randomly inspected by batch.
Inspection method: observe and check, check the material certificate, and do the ignition test.
(2) Non-combustible insulation materials must be used in the following occasions:
1) 800mm in front and back of the electric heater
2) Cross the air duct, pipe and heat insulation layer within 2m on both sides of the firewall.
Check quantity: full check.
Inspection method: observe and check, check the material certificate, and do the ignition test.
(3) The insulation of the air duct and pipe located in the clean room should not be easy to produce dust materials.(Such as glass fiber, short fiber mineral cotton, etc.)
Inspection quantity: full inspection;
Inspection method: observation and inspection.
Performance of common thermal insulation materials
(1) Rubber and plastic products
Closed foaming structure, small thermal conductivity, with excellent adiabatic effect, surface water vapor is not easy to pass through, low water absorption, soft, clean appearance, applicable temperature-40℃ ~105℃, has a good flame retardant effect.
(2) Rock cotton board
With basalt and other ores as the main raw materials, through high temperature melting into fiber, adding an appropriate amount of binder, curing and processing. It has good thermal insulation, sound insulation effect. Convenient construction, energy saving effect is good, building rock wool board has good fire prevention, insulation and absorption performance, mainly used for building walls, firewall, fire doors and elevator well fire and noise reduction.
(3) Glass-wool board
Light capacity weight, large sound absorption coefficient, flame retardant and excellent chemical stability.
(4) Compound silicate
It has the characteristics of high temperature resistance, thin material cost, no pollution, long life and convenient construction. Low thermal conductivity, wide applicable temperature range, non-toxic, pollution-free, no irritation damage to the human body, good adhesion.
(5) Phenolic thermal insulation board
Excellent fire performance, outstanding insulation and energy saving effect, light quality, no water absorption, safety and environmental protection, good size stability, a wide range of uses (wall, air conditioning duct, pipe insulation, equipment room cabinet insulation, equipment insulation). The most prominent feature is non-burning, low smoke, convenient construction.
Construction conditions:
- The building has been capped and the roof is well waterproof.
- The air duct passes the system air leakage test.
- Equipment and water pipe strength test or air tightness test are qualified. Under special circumstances, the insulation construction of the pipeline is allowed to be carried out before the strength test or air tightness test, but the weld shall not be constructed. A thermal insulation distance of about 300mm should be set aside on both sides of the weld, and the disconnected end surface should be closed, and the construction should be conducted after the test.
- For pipes and vertical equipment, all fixed frames, support rings, supports and hangers shall be installed according to the regulations.
- Anti anticorrosion of pipelines and equipment.
- Inabatic materials enter the site and pass the inspection.
- Outdoor construction of heat insulation engineering, rain prevention facilities must be complete and effective.
Thermal insulation construction machine: circular disc saw, hand saw, thermal insulation knife, steel plate ruler, box ruler, hair brush, packing pliers, etc.
Air duct insulation
(1) Rectangular air duct rock wool (or glass wool) felt, plate insulation nail fixed structure
Before bonding the insulation nail, wipe the dust and oil on the air pipe wall, apply the adhesive on the adhesive surface of the pipe wall and the insulation nail, and then stick it later.
The connection of the thermal insulation nail with the surface of the air duct, parts and equipment can be bonded or welded, and the combination shall be firm and shall not fall off.
The distribution of rectangular air duct or equipment insulation nails shall be uniform, the number of:
- The bottom surface —— should not be less than 16 pieces per square meter.
- Side —— should not be less than 10.
- The top surface —— should not be less than 8.
The distance between the first line of insulation nail to the edge of the duct or insulation material shall be less than 120mm.
Cut the insulation material according to the specifications of the air duct, and fix it on the insulation nail.
The thickness of the insulation layer of the duct flange should not be less than 0.8 times that of the duct insulation layer.
The joint with moisture-proof air insulation material should be sealed with adhesive tape. The width of the adhesive tape should not be less than 50mm. The adhesive tape should be firmly pasted on the moisture-proof surface layer, without swelling and falling off.
Inspection quantity: 10% according to the quantity, and not less than 5 places.
Inspection method: observation and inspection.
(2) rectangular duct polystyrene foam board bonding insulation structure
Polystyrene foam plastic points: self-extinguishing type and non-self-extinguishing type.
Before construction, identification —— ignition method, leaving the fire is extinguished.
Bonding method: resin glue and hot asphalt.
Quality requirements for heat insulation construction of air ducts and components
The adiabatic condition of the air duct system components shall not affect the operation function
Inspection quantity: 10% according to the quantity, and not less than 2.
Inspection method: observation and inspection
When the insulation layer of the air duct is fixed by bonding method, the construction shall comply with the following provisions:
(1) The performance of the adhesive should meet the requirements of the use temperature and environmental hygiene, and match with the insulation material.
(2) The adhesive material should be evenly coated on the surface of the duct, parts or equipment, and the insulation material should be close to the surface of the duct, parts and equipment without space.
The longitudinal and transverse joints of the insulation layer should be staggered.
After the insulation layer is pasted, such as dressing or binding, the binding lap place should be uniform and tight; the binding should be moderately tight.
Check quantity: spot check: 10%.
Inspection method: observation, inspection and inspection of material qualification certificate.
Quality inspection of air duct installation:
- Safety problems that should be paid attention to when installing the air duct
- When lifting, it is strictly prohibited to stand under the duct and on the duct.
- Check whether there are heavy objects in the inner and upper surface of the air duct to prevent falling objects from lifting.
- For the long wind pipe, the lifting speed should be carried out synchronously with the beginning of the end to prevent the deformation of the air pipe due to the high flange in the middle part of the air duct.
- The duct lifted to the bracket should be installed in time and not for too long.
- Do not open the holes in advance; when construction is suspended, plates should be affixed to prevent falling objects.
- Use the ladder shall not be missing, do not pad high use.
The upper end of the ladder should be firmly fastened, and the lower end should be taken with anti-skid measures.
When the air supply air branch pipe and the main pipe are connected by the straight pipe form, A diversion device shall be provided at the intubation interface.
- Quality inspection of air duct installation
After the air duct is installed, it can be checked by pulling wire or lifting wire. Generally, as long as the support and hanger is installed correctly and the duct is connected straight, the duct should be able to keep horizontal and vertical. The allowable deviation of duct installation is not more than 3mm / m, and the total deviation is not more than 20mm.
GB50243-2016 Code for Acceptance of Ventilation and Air Conditioning Engineering:
6.2.9 After the installation of the air duct system, the construction quality and appearance inspection shall be conducted according to the requirements of the system category. After being qualified, the air duct system shall be inspected closely. The air leakage amount shall meet the design requirements and Article 4.2.1 of this specification, except for the following provisions:
- When the tightness inspection of the air duct system fails, except for repairing the unqualified system, the inspected party shall apply for reinspection or reinspection.
2 During the purification air conditioning system, the N1 ~N5 system shall follow the regulations of high pressure system; the N6 ~N9 system, and the working pressure is less than or equal to 1500Pa, according to the regulations of medium pressure system.
Inspection quantity: micro pressure system with full observation inspection according to process quality requirements; low voltage system with sampling inspection according to scheme; medium voltage system with sampling inspection according to scheme I; high voltage system with full inspection.
- Light leakage detection method:
Safe light source with certain intensity is used for detection. Hand-held light source can be not less than 100W with protective cover or other low voltage light source.
During detection, the light source can be placed on the inside or outside of the duct, but the opposite side should be dark environment. The detection light source moves slowly along the detected interface part and the joint, and observe on the other side. When a light ray is found, it indicates that there is an obvious air leakage, and a record should be made.
Light leakage should be detected in sections, mainly with the main pipe and the main pipe. The low pressure system duct shall pass every 10m joints, and the average 100m joints are not more than 16; the medium pressure system duct shall pass every 10m joints, and the average 100m joints are not more than 8 are qualified.
- Air leakage capacity test
(1) Basic principles
In an ideal state, the gas is injected into a closed container to keep the pressure in the container constant, and then the injected gas flow rate is equal to the leakage amount of the closed container.
(2) Detection method
Connect the air outlet of the fan to the tested hose. The air duct shall be blocked except for the connection with the hose for the test device and a pressure gauge from above. When the air leakage detector is started and the fan speed is gradually increased, the pressure in the duct will gradually increase through the hose into the duct. When the air duct reaches the required test pressure, adjust the fan speed of the detector to keep the pressure in the air duct constant, then the air volume at the measured fan inlet is the air leakage volume of the measured air duct under the pressure.
- Finished product protection
- The installed air duct should ensure that the surface of the air duct is smooth and clean, and the outdoor air duct should have rain and snow prevention measures.
2 For the air duct of the suspended construction, the opening should be closed to prevent debris from entering.
3 When the air duct is extended into the structural air duct, the steel plate mesh should be installed at the end to prevent debris from entering the metal air duct when the system is running.
- In sites with more cross operations, it is strictly prohibited to use the installed air duct as supports, cranes and brackets, and other supports and hanger are not allowed to be welded or hung on the air duct flange and air duct support and hanger.
- Quality records
Quality inspection and evaluation record form shall be filled in after the installation of the air duct and parts.
Quality problems that should be paid to in the installation of air duct and parts
1, hanger does not brush oil, boom is too long
Enhance the sense of responsibility, after the system should be brush oil in time, the boom should be carefully checked when the elevation
2 branches, the hanger spacing is too large
Carry out the specification, after the installation, carefully review whether the spacing is too large phenomenon
3 Flange, waist band open welding
Carefully check before installation, find out the problems, and repair them in time
4 The screw leak through, not tight, loose
Increase the sense of responsibility, the flange hole distance should be adjusted in time
5 The canvas mouth is too long and twisted
Riveting canvas should be straight, straight, iron sheet to press the canvas, do not leak riveting
6 The modified pipe and rivet holes are not blocked
After modification, the tin welding or sealing glue should be applied
7 The mat material falls off
Strictly according to the process to do, the flange surface should be clean
8 The purification pad is not coated with sealant
Study norms carefully
9 Fire prevention valve action is not flexible
The valve body shall not touch the actuator and the melting plate
10 All kinds of tuyere are not flexible
The blade should be parallel and firmly not touched with the outer frame
11 The tuyere installation is not required
Strictly implement the requirements of regulations and specifications for tuyere installation